Assignment Name:

Country:

Design and Construction of a Piped Water Supply for Kumi Hospital plus Ancillary Works and Activities

Uganda

Location within country:

Positions provided by WE Consult:

Ongino Sub-County, Kumi District

Project Manager, Topographic surveyor,Sr.Hydrogeologist
Jr. Hydrogeologists, Construction Supervisor, Sr. Water and Civil Engineer, Community mobiliser, staff  for all construction works

Name and Address of client:

No. of  staff months:

Funding agency:

Kumi Hospital
P.O. Box 8
Kumi

20

The Charitable Foundation (Australia) / Christian Blind Mission International (Australia)

Start Date
(Month / Year)

Completion Date (Month/ Year)

Total contract price of the assignment

12/04

09/06

EUR 339,316

Name of Associated Firm(s), if any:

Name of Senior staff of WE Consult involved:

 

C.W.B. Mulders (Project Manager)
R.R. Sloots (Financial Manager)
T.O. Olukwita (Hydrogeologist)
V. Akiiki Byarugaba (Construction Supervisor)
S. Okiror (Community mobiliser)

Narrative description of project:

Following WE Consult’s water resources assessment study, the company was contracted to design and construct a piped water supply for Kumi Hospital. The contract includes a large community component, involving the drilling of 7 boreholes and the construction of 1 shallow well for the communities situated between the lake intake and the Hospital, creation of hygiene and sanitation awareness and development of water user committees. The construction of the piped water supplies includes the construction of a rising main of 8 km, rehabilitation of existing storage tanks, construction of pump house and staff house, water treatment and an elaborate distribution network towards all hospital buildings and a number of tap stands.
 In addition, a hygiene and sanitation plan is developed for the hospital following a participatory approach. The sanitation situation of the hospital is improved through the construction as well as upgrading of latrine facilities. The hospital is trained in the technical and financial management of the water supply.

Description of services provided by your staff:

  • Community mobilization, training WUC
  • Topographic survey
  • Geophysical borehole survey
  • Hygiene and sanitation promotion in three parishes
  • Drilling of 7 boreholes and drilling supervision
  • Detailed engineering design, incl. Tender docs
  • Training of borehole mechanics
  • Selection of contractors for piped water supply
  • Mobilisation of contractors (preliminaries)
  • Construction and construction supervision
  • Training of water operational staff
  • Develop Hygiene Plan for Hospital
  • Implement Hygiene Plan
  • Development of participatory sanitation action plan hospital
  • Construction and upgrading of VIP latrines
  • Latrine construction supervision
  • Development of (financial) management & monitoring plan
  • Training in (financial) management and monitoring
  • Commissioning and Handover of system
  • Implementation of management and monitoring plan
  • Project evaluation (6 months after commissioning)